Army Corps Delays DAPL Easement
Washington, DC – On Monday, November 14, the Army Corps of Engineers said in a statement that “additional discussion and analysis” was “warranted” before they could grant an easement needed by Dakota Access Pipeline to start construction on land near Lake Oahe.
UPDATE: Army Corps of Engineers delays granting easement for #DakotaAccessPipeline construction until further analysis & discussion. #NoDAPL
— Unicorn Riot (@UR_Ninja) November 15, 2016
The Army Corps statement clearly laid out that construction “cannot” occur around the lands of Lake Oahe.
“…construction on or under Corps land bordering Lake Oahe cannot occur because the Army has not made a final decision on whether to grant an easement.” Army Corps statement – Nov. 14, 2016
Here is the full statement:
This Army Corps statement on Monday denying an easement comes a week after Dakota Access made an election night statement claiming that:
“Dakota Access remains confident that it will receive the easement for these two strips of land adjacent to Lake Oahe in a time frame that will not result in any significant delay in proceeding with drilling activities under Lake Oahe.” Dakota Access Statement – Nov. 8, 2016
In their November 8th statement, Dakota Access also denied the existence of claims made by the Army Corps that Dakota Access had agreed to slow down their construction.
Construction has continued despite two requests from the Army Corps that DAPL voluntarily stop construction. Dakota Access has created a militarized construction site, complete with Hesco bastions and razor wire to reinforce war-time barriers around the drill site needed to use a horizontal drill to bore under the Missouri River.
Dakota Access builds militarized construction site w/ hesco walls & razor wire to protect oil pipeline from water protectors. #NoDAPL pic.twitter.com/TembKYZXfW
— Unicorn Riot (@UR_Ninja) November 11, 2016
In the statement released November 14, the Army Corps said they continue “to welcome any input that the Tribe believes is relevant to the proposed pipeline crossing or the granting of an easement.”
The Army Corps is expected to hear a lot of input on November 15, 2016, as a national call for #NoDAPL Day of Action at Army Corps of Engineers takes place in cities across the world.
It must be noted that the statement by the Army does not include a definitive “no“; it is merely delaying the process of granting the easement. Here is the full Army Corps of Engineers statement:
“Today, the Army informed the Standing Rock Sioux Tribe, Energy Transfer Partners, and Dakota Access, LLC, that it has completed the review that it launched on September 9, 2016. The Army has determined that additional discussion and analysis are warranted in light of the history of the Great Sioux Nation’s dispossessions of lands, the importance of Lake Oahe to the Tribe, our government-to-government relationship, and the statute governing easements through government property.
The Army invites the Standing Rock Sioux Tribe to engage in discussion regarding potential conditions on an easement for the pipeline crossing that would reduce the risk of a spill or rupture, hasten detection and response to any possible spill, or otherwise enhance the protection of Lake Oahe and the Tribe’s water supplies. The Army invites discussion of the risk of a spill in light of such conditions, and whether to grant an easement for the pipeline to cross Lake Oahe at the proposed location. The Army continues to welcome any input that the Tribe believes is relevant to the proposed pipeline crossing or the granting of an easement.
While these discussions are ongoing, construction on or under Corps land bordering Lake Oahe cannot occur because the Army has not made a final decision on whether to grant an easement. The Army will work with the Tribe on a timeline that allows for robust discussion and analysis to be completed expeditiously.
We fully support the rights of all Americans to assemble and speak freely, and urge everyone involved in protest or pipeline activities to adhere to the principles of nonviolence.” – Army Corps Statement – Nov. 14, 2016
Unicorn Riot will continue to regularly provide direct updates about resistance to the Dakota Access Pipeline. Follow our media on Twitter, Facebook, and our website for more information surrounding the ongoing struggles against the Dakota Access Pipeline.
To support our volunteer-operated, horizontally-organized, non-profit media collective please consider a tax-deductible donation:
Unicorn Riot’s coverage of the anti-Dakota Access Pipeline struggle #NoDAPL from early summer 2016 to present:
March – May 2016
- March 29th, “Tribal Citizens Prepare to Blockade Bakken Oil Pipeline“.
- April 3rd, “Tribal Citizens Build Camp in Path of Oil Pipeline“.
- May 5th, “Sacred Stone Camp Resists Dakota Access Pipeline“.
- May 27th, “Dakota Access Pipeline Blockade Enters 2nd Month“.
August 2016
- After covering the camp in the spring of 2016, Unicorn Riot returned to Standing Rock Reservation on Wednesday, August 10th, when Standing Rock tribal members and allies blocked the entrance to the Dakota Access Pipeline construction site.
- On Thursday, August 11th, a dozen or so people were arrested blocking the construction site entrances.
- Day 3, Friday, the fight to protect land & water intensified around the construction sites of the Dakota Access Pipeline.
- On the 4th day, the pipeline resistance encampment swelled and prepared for more action.
- Monday, August 15th, land defenders stormed the construction site halting construction, and the next day construction was halted as well.
- August 17th saw State Police begin checkpoints, roadblocks, and psyops as protesters united to defend water.
- August 24th, camps prepared as Federal injunction hearing looms.
- Camps Organize to Stay as Injunction Postponed.
- On August 31st, Non-Violent Direct Action Stopped DAPL Construction for Over 6 Hours.
September 2016
- September 6, indigenous water protectors swarmed Dakota Access Pipeline site, stopped work
- September 7, Uŋpa Nuŋpa was interviewed about ongoing #noDAPL actions
- North Dakota highway patrol refused to release email correspondence with Energy Transfer Partners
- September 8, ND National Guard took over Dakota Access Pipeline checkpoints
- Friday, September 9, US Govt. overruled federal judge and requested pipeline construction halted at Lake Oahe
- Meanwhile, cultural activities continued at #NoDAPL camps despite more arrests/warrants
- September 13, 20 were arrested during #NoDAPL lockdown, including 2 Unicorn Riot journalists
- September 14, direct actions continued against Dakota Access Pipeline while legal repression intensified
- On September 16 a federal judge dissolved the unconstitutional temporary restraining order Dakota Access, LLC had filed against Stranding Rock tribal members
- September 19, as solidarity protests spread nationwide, the federal appeals court ordered construction temporarily stop on Dakota Access segment as Solidarity Protests Spread Nationwide
- September 21, #NoDAPL noise demo demanded freedom for jailed water protector Olowan Martinez
- September 22, water protectors disrupted the annual meeting of the North Dakota Petroleum Council
- September 25, water protectors planted trees on DAPL construction site
- In Iowa on September 26, a non-violent direct action from the Mississippi Stand camp stopped DAPL construction for the day
- September 26, a caravan of water protectors stopped work at DAPL site
- September 27, militarized police arrested 23 water protectors in DAPL work stoppage
- September 29, a #NoDAPL solidarity action took place at MN Enbridge office
October 2016
- October 3rd-4th saw the “Toxic Tour,” Governor debate disruption, and water protectors attend their court arraignment
- October 4, we learned North Dakota Governor Dalrymple’s email inbox was full of support for #NoDAPL
- October 5, Buffer Zone Holds as Caravans Continue to Disrupt DAPL – New Felony Charges
- October 7, 6 Arrested in Iowa #NoDAPL Action, Including Unicorn Riot Journalist
- October 8, Iowa Water Protectors Blockade DAPL Drill Site Twice in 24 Hours
- October 9, Federal Appeals Court Rules to Allow DAPL Construction
- October 10, 27 Arrests After Water Protectors Pray at DAPL Site on Indigenous People’s Day
- October 12, Lockdown Stops DAPL Construction in Iowa, 3 Arrested, Including Unicorn Riot Journalist
- October 14, Emails Show North Dakota Budget Bureaucracy Behind #NoDAPL Policing
- October 16, Direct Actions Continue to Stop DAPL Construction in Iowa and North Dakota
- October 17, Four Unicorn Riot Journalists Face Charges For Covering #NoDAPL
- October 17, Water Protectors Blockade Highway in Bismarck, Some Charges Dropped
- October 20, As DAPL Construction Advances, Water Protectors Continue Direct Action
- October 22, Water Protectors’ Prayer Walk Ends up with 127 Arrests, Including Unicorn Riot Journalist
- October 23, Law Enforcement Attack Private Drone as Water Protectors Erect Blockade & New Winter Camp
- October 24, Mississippi Stand Blockades Iowa DAPL Drill Waste Site, Drilling Stops
- October 25, Records Release: Morton County’s Law Enforcement Mutual Aid Assistance Agreement
- Hundreds Flood Minneapolis City Hall to Demand Local Sheriff Withdraw from North Dakota
- October 26, Tensions Rise as Pipeline Construction Nears #NoDAPL Blockade
- October 27, Police and Military Attack Oceti Sakowin Treaty Camp
November 2016
- November 1, #NoDAPL Solidarity Rally & Sit-In in Minneapolis Prods Sheriff into Removing Deputies
- November 1, DAPL Resistance Continues Despite Advancing Construction
- November 2, Police Attack Water Protectors Defending Sacred Sites
- November 5, DAPL Construction Nears US Army Corps Land While Still Lacking Permits
- November 6, Water Protectors Attempt to Reclaim Sacred Burial Site, Demonstrate in Cemetery
- November 8, Dakota Access Announces Plan to Drill Under Missouri River Within Weeks
- November 11, Dakota Access Pipeline Work Stopped As Water Protectors Storm Site; 30+ Arrested
- November 14, #NoDAPL Water Protectors March on ND State Capitol after Caravan Disrupts Construction
- November 14, Mississippi Stand Goes Inside Pipeline and Shuts Down DAPL Construction